Now open

A sign displays

The Atlantic and Vernon Street  ‘S-curve’ is now open and improvements include: 

  • Raised landscaped medians
  • Enhanced pedestrian crosswalk with lighting
  • ADA-compliant curb ramp upgrades
  • Green bike lanes for better visibility
  • Lane reductions to slow vehicle speeds
  • To reduce collisions, left-hand turning restrictions onto Atlantic Street were added at smaller intersections: Almond St., Brittain St., Folsom Rd., Walnut St., and Jefferson St.
Map of the project area along the Vernon/Atlantic S-curve between Lincoln and Yosemite Street. 
Project map with renderings of medians, crosswalks, roadway directional markings, and a bike lane.

Enlarge map

The estimated construction cost is $1 million. Roseville has received approximately $487,000 in Highway Safety Improvement Program Grant Funds. Other funding sources are local Transportation Development Act funding and Highway Users Tax fees.

Construction phase: Winter 2025 - spring 2026     
Open to the public: Late June 2026                         

During the planning phase, a community open house was held at the Civic Center, 5 - 6:30 p.m. on June 29, 2022. Attendees came to learn about the planned improvements, ask questions, and talk with the project team.

Be notified and subscribe to the Public Works email newsletter and follow us on social media. 

Have questions? Contact Public Works.
(916) 746-1300
Email